top of page

Method Statements (Bridge works) Methodology

CONTENTS



1. Introduction

2. Structural Excavation

3. Sub-Surface Investigation

4. Confirmatory Bore Holes

5. Bored cast-in-situ piles using conventional rig

6. Initial Pile load test

7. Pile cap

8. Well Steining

9. Well Sinking

10. Well bottom plug

11. Well cap

12. Sub structure

13. Filter media and backfilling

14. RCC Girder

15. Deck slab

16. PSC Girder and Deck slab

17. Box Girder

18. Fixing of POT / PTFE bearings


---x---


1. INTRODUCTION


1.1 SCOPE

This document outlines the procedure for the method of construction of major items of Bridge works as per approved drawings and specifications of the Project.

The Standard Specifications for Road and Bridge Works of Ministry of Shipping, Road Transport & Highway (MoSRTH) shall be consulted for the details which are not covered in this document.


1.2 FIELD OF APPLICATION

1. Structural Excavation

2. Sub-Surface Investigation

3. Confirmatory Bore Holes

4. Bored cast-in-situ piles using conventional rig

5. Initial Pile load test

6. Pile cap

7. Well Steining

8. Well Sinking

9. Well bottom plug

10. Well cap

11. Sub structure

12. Filter media and backfilling

13. RCC Girder

14. Deck slab

15. PSC Girder and Deck slab

16. Box Girder

17. Fixing of POT / PTFE bearings


1.3. REFERENCES

1. Concessionaire Agreement

2. MoSRTH Specifications for Road and Bridge Works



---x---


2. STRUCTURAL EXCAVATION



2.1 OBJECTIVE:

To out line the procedure for method of Excavation for the construction of foundations for bridges, culverts, retaining walls, headwalls, cutoff walls, pipe culverts and other similar structures to the required dimensions and levels conforming to approved drawings and project specifications.


2.2 CONSTRUCTION EQUIPMENT:

• Excavator

• Dump Trucks


2.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for execution of structural excavation works:


a After the site has been cleared, the limits of excavation shall be set out true to lines, curves and slopes.

b Excavation shall be taken to the width of the lowest step of the footing and the sides shall be left plumb where the nature of soil allows it. Where the nature of soil or the depth of the trench and season of the year do not permit vertical sides, put up necessary shoring, strutting and planking or cut slopes to a safer angle.

c Normally, open foundations shall be laid dry. Where water is met with in excavation due to stream flow, seepage, springs, rain or other reasons, adequate measures such as bailing, pumping, constructing diversion channels, bunds, depression of water level by well point system, cofferdams and other necessary works to keep the foundation trenches dry when so required and to protect the green concrete against damage by erosion or sudden rising of water level.

d The bottom of the foundation shall be leveled both longitudinally and transversely. Before footing is laid, the surface shall be slightly watered and rammed.

e If there are any slips or slip-outs in the excavation, these shall be removed.

f Near towns, villages and all frequented places, trenches and foundation pits shall be securely fenced, provided with proper caution signs and marked with red lights at night to avoid accidents. Take adequate protective measures to see that the excavation operations do not affect or damage adjoining structures.

g Backfilling shall be done with approved material after concrete is fully set and carried out in such a way as not to cause undue thrust on any part of the structure. All space between foundation concrete and the sides of excavation shall be refilled to the original surface in layers not exceeding 150 mm compacted thickness. The compaction shall be done with the help of suitable equipment such as mechanical tamper, rammer or plate vibrator after necessary watering, so as to achieve a density not less than the field density before excavation.

---x---

3. SUB-SURFACE INVESTIGATION



3.1 OBJECTIVE:

To out line the procedure for method of complete sub-surface investigation of strata in which pile foundations are proposed shall be carried out in advance and by in-situ pile tests conforming to approved drawings and project specifications.


3.2 CONSTRUCTION EQUIPMENT:

• Rig

• Standard Penetration Test Sampler


3.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for sub-surface investigation:


a At least one bore-hole for every foundation of the bridge shall be executed, depth of the boring shall not be less than:

i) 1.5 times estimated length of pile in soil but not less than 15m beyond the probable length of pile.

ii) 15 times diameter of pile in weak/jointed rock but minimum 15m in such rock.

iii) 4 times diameter of pile in sound, hard rock but minimum 3m in such rock.

b The investigation shall also include location of ground water table and other parameters including results of chemical tests showing sulphate and chloride content and any other deleterious chemical content in soil and / or ground water, likely to affect durability.

---x---

4. CONFIRMATORY BORE HOLES



4.1 OBJECTIVE:

To out line the procedure for the method of execution of confirmatory bore holes conforming to approved drawings and project specifications.


4.2 CONSTRUCTION EQUIPMENT:

• Conventional soil drilling machine including accessories

• Water Pump

• Electrical Generator


4.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for execution of confirmatory bore holes:


a The Borehole point’s location will be the location of the foundation of the particular bridge structure and the no. of such bore holes and its exact location will be as decided by the Engineer.


b Confirmatory Bore holes will be executed on land based method by deploying rotary drilling equipment.


c After the finalizing of the bore hole location the casing will be driven up to the collapsible strata by drilling and hammering the casing tube.


d Further drilling will be done with Bentonite Mud Circulation up to the head rock level. The depth of the exploration will be at least 1.5 times the minimum depth of the foundation.


e Undisturbed samples will be collected ensuring that their moisture content and structure do not get altered during the recovery of the sample. Undisturbed Samples will be collected as per IS 2132 in reusable open drive thin walled MS tubes of 100 mm diameter tube. The undisturbed samples are waxed at both ends immediately after collection, numbered and labeled properly for identification.


f The standard penetration test sampler will be as per IS 2131. The driving weight of 63.5 Kg weight is provided with suitable arrangement for controlling the height of fall as 75 cms. In Standard Penetration test the blow counts for every penetration of 15 cms, up to the total penetration of 45 cms are recorded. The standard penetration test blow count, “N” is reckoned as the total number of blows for the second and third penetration increments adding to 30 cms. The “N” value is indicative of the relative density of cohesion less soils and consistency of cohesive soils.


g The sample retrieved from Standard penetration test spoon was inspected for visual identification of strata. The samples are preserved in polythene bags, duly numbered and N values mentioned for proper identification.


h The field records shall contain details of bore location, the elevation of the ground surface with respect to permanent bench mark, elevation of the water table, upper boundary of each of the successive soil strata encountered, general information regarding the soil type obtained by visual inspection, the value of resistance obtained by means of standard penetration test.

I Proper care shall be taken in handling and labeling of the samples.


4.4 OBSERVATION SHEET:


CONFIRMATORY BORE HOLES


Bridge No. Date of Execution:

Bore Hole No. Method: Rotary Drilling.

RL: Working Tech: Land based method.

GL:


Depth

(m) Visual Soil Description Graphic Log Samples Penetration Test N value

Depth (m) Type No. 15 cms 30 cms 45 cms


---x---
























5. BORED CAST-IN-SITU PILES USING CONVENTIONAL RIG



5.1 OBJECTIVE:

To out line the procedure for the method of construction of bored cast-in-situ piles conforming to approved drawings and project specifications.


5.2 CONSTRUCTION EQUIPMENT:

• Heavy piling tripod

• Reciprocating / Centrifugal pumps

• Bentonite mixing plant

• Boring accessories and tools

• Concreting accessories

• Electrical Generator

• Welding transformer / Gas cutting sets


5.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of bored cast-in-situ pilling works:


a Pile points will be established on ground from the approved established survey station by using total station based on the approved drawing.


b Bored Cast-in-situ piles can be executed in any of the following two methods

1. Percussion method

2. Rotary Method


c Shift and center the piling tripod over the pile point established on the ground.


d Normally temporary casing pipe will be pitched / installed by making a naked borehole of about 1 meter to 1.5 meter in the ground of the pile location and drive the temporary casing up to the required depth by hammering and boring either by conventional piling rig or by rotary drilling equipment.

To position this temporary casing with exact pile location two reference points are to be fixed on the ground approximately perpendicular to each other from the center point of the pile. Normally these reference points will be distanced from the casing with the conventional measurement.


e Pile boring can be done either of the two following methods

1. Direct Mud Circulation Method (DMC Method)

2. Reverse Mud Circulation Method (RMC Method)


1. Direct Mud Circulation Method

In DMC method boring will be done with the help of conventional piling rig i.e. heavy tripod coupled with power winch and an attachment of DMC rods and chisel. Chisel is normally 75mm lesser than the diameter of the pile. This reduction of diameter is for limiting the over breakage of the sides of the borehole which happens due to the oscillation of the chisel fitted to the long length of the DMC rods. With the help of the chisel boring will be done. In the process of boring bentonite slurry (drilling mud) will be continuously fed/injected in the bottom of the borehole through DMC pipes. Due to the penetration of the chisel and continuous flow of bentonite slurry soil will get agitated and the agitated soil will come out from the borehole along with the overflowing bentonite slurry. This forms the borehole.


2. Reverse Mud Circulation Method

In this method boring will be done either by Percussion or by Rotary method. In percussion method the bored material will be bailed out by suction either by bailor or by pumps

In rotary method bored material will be directly scooped out either by augur or by bucket.

In both the methods bentonite slurry is pumped at the top of the borehole.


f After reaching the final level boring is stopped and bentonite slurry is fed for some more time to allow the floating material to come out and the bentonite coming out reaches the standard specific gravity.

The reinforcement cages that are already made as per the design were lowered in suitable lengths and the pieces will be joined together by tack welding.


g Before concreting the borehole has to be flushed again with bentonite slurry to remove any sediment material left within the bore hole. After flushing tremie pipes will be lowered up to the bottom of the borehole for concreting. On top of the tremie pipe suitable capacity funnel is to be fitted. Before the first pour the funnel neck is covered by a metallic cover and it is removed after sufficient concrete has been poured into the funnel. This ensures that first pour concrete displaces the bentonite slurry and gives sufficient embedment to the tremie pipe. Likewise concrete is to be built up to the required level i.e. above the cutoff level to clear off the contaminated top concrete mixed with bentonite and at each stage crosschecks will be done so that the minimum embedment of the tremie pipe is ensured. The laitance will be chipped off at a later stage so that sound concrete is ensured at the cutoff level.

---x---















6. INITIAL PILE LOAD TEST



6.1 OBJECTIVE:

To out line the procedure for the method of Initial Pile load test conforming to approved drawings and project specifications.


6.2 CONSTRUCTION EQUIPMENT:

• Hydraulic Jacks

• Pressure gauge and Dial gauges

• Datum bar


6.3 CONSTRUCTION METHODOLOGY FOR INITIAL VERTICAL PILE LOAD TEST:

The following sequence of activities shall be carried out for Initial vertical pile load test:


The pile head should be chipped off to natural horizontal plane till sound concrete is met. The projecting reinforcement should be cut off or bent suitably and the top surface finished and leveled with plaster of paris or similar synthetic material where required. A bearing plate with a hole at the center should be placed on the head of the pile for the jacks to rest.


The test should be carried out by applying a series of vertical downward incremental load each increment being of about 20% of safe load on the pile.

The reaction may be obtained from the following:


i. Kentledge placed on a platform supported clear of the test pile in case of load test below under–pinned structure, the existing structure if having adequate weight and suitable construction may serve as kentledge. The center of gravity of the kentledge should generally be on the axis of the pile and the load applied by the jack should also be coaxial with this pile.


ii. Anchor piles with center-to-center distance with the test pile not less than three times the test pile shaft diameter subject to minimum of two meters. If the anchor piles are permanent working piles it should be ensured that their residual uplift is with in limits. Care should be exercised to ensure that the datum bar supports are not affected by heaving up of the soil.


Settlement shall be recorded with minimum 2 dial gauges for single pile and 4 dial gauges of 0.01mm sensitivity for groups, each positioned at equal distance around the piles and normally held by datum bars resting on immovable supports at a distance of 3D from the edge of the piles where D is the pile stem diameter of circular piles.


The safe load on a single pile for the initial test should be least of the following:


i. Two-thirds of the final load at which the total displacement attains a value of 12mm unless other wise required in a given case on the basis of nature and type structure in which case, the safe load should be corresponding to the stated total displacement permissible.

ii. 50% of the final load at which the total displacement equals 10% of the pile diameter in case of uniform diameter piles and 7.5% of bulb diameter in case of under reamed piles.


6.4 SUMMARY SHEET FOR INITIAL VERTICAL PILE LOAD TEST:

1. Location :

2. Diameter of Pile :

3. Founding Level :

4. Cut-off Level :

5. Length of Pile :

6. Reinforcement Details :

7. Grade of Concrete :

8. Mix Proportion by Weight :

9. Design Load :

10. Test Load (2.5 x Design Load) :

(The reaction to be made available for the test should be 25 % more than the final test load proposed to be applied.)

11. Kentledge Load :

(Separate calculation sheets will be provided for each location depending upon the actual load required for the specific case)

12. Hydraulic jack :

a) Ram Diameter :

b) Ram Area :

c) Jack Capacity :

13. Pressure Gauge :

14. Increments :

(20 % of the safe load)

15. Micrometers / Dial Gauges :

16. Gross settlement :

17. Rebound :

18. Net Settlement :

19. Date of Commencement :

20. Date of Completion :






6.5 OBSERVATION SHEET FOR INITIAL VERTICAL PILE LOAD TEST:

Date Sl No Time Percentage of Load Applied Load applied Pressure gauge reading Dial Gauge Reading Average Settlement Gross Settlement Rebound

From To A B


6.6 CONSTRUCTION METHODOLOGY FOR INITIAL HORIZONTAL PILE LOAD TEST:

The following sequence of activities shall be carried out for Initial horizontal pile load test:


The test may be carried out by introducing a hydraulic jack with gauge between two piles under test or the reaction may be suitably obtained otherwise .If it is conducted by jack located by between two piles, the full load imposed by the jack shall be taken as the lateral resistance of each pile . The loading should be applied in increments of about 20 percent of the estimated safe load.


The next increment should be applied after the rate of displacements nearer to 0.1 mm per 30 minutes.


Displacements shall be read by using at least two dial gauges duly checked and calibrated for 0.01 mm sensitivity spaced at 30 cm and kept horizontally one above the other on the test pile and the displacement interpolated at cutoff level from similar triangles where cutoff level is unapproachable and for approachable cutoff level, how ever, one dial gauge placed diametrically opposite to the jack shall directly measure the displacement. Where it is not possible to locate one of the dial gauges in the line of the jack axis, then two dial gauges may be kept at a distance of 30 cms at a suitable height and the displacement interpolated at load point from similar triangles


The safe lateral load on the pile shall be taken as the least of the following:


a) Fifty percent of the final load at which the total displacement increases to 12mm;

b) Final load at which the total displacement correspond to 5mm; and Load corresponding to any other specified displacement as per Performance requirements.


6.7 SUMMARY SHEET FOR INITIAL HORIZONTAL PILE LOAD TEST:

1. Location :

2. Diameter of Pile :

3. Founding Level :

4. Cut-off Level :

5. Length of Pile :

6. Reinforcement Details :

7. Grade of Concrete :

8. Mix Proportion by Weight :

9. Design Load :

10. Test Load (2 x Design Load) :

11. Hydraulic jack :

a) Ram Diameter :

b) Ram Area :

c) Jack Capacity :

12. Pressure Gauge :

13. Increments :

(20 % of the safe load)

14. Micrometers / Dial Gauges :

15. Gross settlement :

16. Rebound :

17. Net Settlement :

18. Date of Commencement :

19. Date of Completion :

6.8 OBSERVATION SHEET FOR INITIAL HORIZONTAL PILE LOAD TEST:

Date Sl No Time Percentage of Load Applied Load applied Pressure gauge reading Dial Gauge Reading Average Settlement Gross Settlement Rebound

From To A B



---x---









7. PILE CAP



7.1 OBJECTIVE:

To out line the procedure for the method of construction of Pile cap conforming to approved drawings and project specifications.


7.2 CONSTRUCTION EQUIPMENT:

• Excavator

• Form work accessories

• Generator

• Welding transformer / Gas cutting set

• Batching plant

• Concrete pump / Crane and bucket

• Water pump


7.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of Pile cap works:


a The location of the pile cap is marked on the ground using a Total Station from the

reference coordinates already fixed.


b Earthwork Excavation shall be taken up as per the approved Earth Work Excavation Methodology.


c PCC bottom level is to be achieved. Concreting of the leveling course will be done and the top surface made true to level.


d Pile chipping will be done with the help of jack hammers not earlier than seven days of pile casting.


e Reinforcement tying of the Pile Cap as per the approved drawing will be done for the Pile Cap. Laps are provided in staggered manner wherever required.


f After the placing of formwork, Concreting will be done ensuing proper compaction. The top surface is made true to level.


g Dewatering shall be done wherever necessary for laying concrete.


h Proper curing arrangement shall be made.

---x---

8. WELL STEINING



8.1 OBJECTIVE:

To out line the procedure for the method of construction of Well steining conforming to approved drawings and project specifications.


8.2 CONSTRUCTION EQUIPMENT:

• Batching plant

• Concrete pump / Crane and bucket

• Submergible pump


8.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of Well steining works:


a Steining built in the first lift above the well curb shall not be more than 2 metres and in subsequent lifts it shall not exceed the diameter of the well or the depth of well sunk below the adjoining bed level at any time. The first lift of steining shall be cast only after sinking the curb at least partially for stability. Concreting of steining may be carried out in subsequent lifts of about 2 to 2.5 metres.

b The steining of the well shall be built in one straight line from bottom to top such that if the well is tilted, the next lift of steining will be aligned in the direction of the tilt. The work will be checked carefully with the aid of straight edges of sufficient lengths. Plumb bob or spirit level shall not be used for alignment.

c The height of steining shall be calibrated by making at least 4 gauges, preferably in traffic direction and in a direction normal to traffic direction on the outer periphery of the well each in the form of a 100mm wide strip painted on the well, with every metre mark shown in black paint. The gauges shall start with zero at the bottom of the cutting edge. Marking of the gauges shall be done carefully with a steel tape.

d After reaching the founding level, the well steining shall be inspected to check for any damage or cracks and take remedial measures.

---x---










9. WELL SINKING



9.1 OBJECTIVE:

To out line the procedure for the method of execution of well sinking conforming to approved drawings and project specifications.


9.2 CONSTRUCTION EQUIPMENT:

• Crane with Grab bucket

• Submersible pump

• Chisels

• Aqua-header for cutting rocky strata

• Diving helmets and accessories


9.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for well sinking:


a The well shall be sunk by excavating material uniformly from inside the dredge hole. Use of water jetting, explosives and divers may be adopted for sinking of wells through difficult strata.

b Normally dewatering of well should not be permitted as a means for sinking the well. It also shall never be resorted to if there is any danger of sand blowing under the well. Dewatering shall however be done when well is to be founded into rock.

c Kentledge shall be placed in an orderly and safe manner on the loading platform and in such a way that it does not interfere with the excavation of the material from inside the dredge hole and also does not in any way damage the steining of the well.

d Where tilts are present or there is a danger of well developing a tilt, the position of the load shall be regulated in such a manner as to provide greater sinking effort on the higher side of the well.

e Water jetting may be employed for well sinking wherever necessary.

f Use of divers may be made both for sinking purpose like removal of obstructions, rock blasting and for inspection. All safety precautions shall be taken for sinking with divers. Only persons trained for the diving operation shall be employed and they shall work under expert supervision.







9.4 OBSERVATION SHEET:


HISTORY OF SINKING OF WELL No. ______



Date Steining Sinking Depth of sump below cutting edge Strata met with Kentledge Quantity of dredged material Report regarding obstacles or sand below during sinking Report any special method of sinking employed Remarks Signature of supervising officer

RL of bottom of cutting edge RL of top of steining before casting RL of top of steining after casting Height of steining cast (Col.4-Col.3) Total ht. of steining incl. curb & cutting edge (Col.4-Col.3) RL at which cutting edge is placed Initial gauge reading Final gauge reading Sinking during the day (Col.9-Col.8) RL of bottom of cutting edge (Col.7-Col.8) Weight Eccentricity along x-axis Eccentricity along y-axis

m m m m m m m MT m m cum

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21



---x---

10. WELL BOTTOM PLUG



10.1 OBJECTIVE:

To out line the procedure for the method of construction of Well bottom plug conforming to approved drawings and project specifications.


10.2 CONSTRUCTION EQUIPMENT:

• Batching plant

• Concrete pump / Crane and bucket

• Tremie funnel and pipes

• Submergible pump


10.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for the construction of Well bottom plug:


a Concrete for the bottom plug shall be laid by tremie pipe method. Tremie concrete when started shall be continued without interruption for full concreting in the bottom plug.

b Before commencing plugging, all loose material from the bottom of the well shall be removed.

c Concreting shall be done in one continuous operation till the dredge hole is filled upto the required height and thereafter sounding shall be taken upto ensure that the concrete has been laid to the required height.

d Least disturbance shall be caused to the water inside the well while laying concrete in the bottom plug.

e Concrete shall not be disturbed in any way for at least 14 days.

f In order to check any rise in the level of the bottom plug soundings should be taken at the close of concreting and once every day for the subsequent 3 days.

g The soundness of the bottom lug maybe tested by dewatering the well by 5 metres below the surrounding water level and checking the rise of water. The rate of rise shall preferably be less than 10 cms per hour.

---x---







11. WELL CAP



11.1 OBJECTIVE:

To out line the procedure for the method of construction of Well cap conforming to approved drawings and project specifications.


11.2 CONSTRUCTION EQUIPMENT:

• Excavator

• Form work accessories

• Generator

• Welding transformer / Gas cutting set

• Batching plant

• Concrete pump / Crane and bucket

• Water pump


11.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of Well cap works:


a The location of the well cap is marked on the ground using a Total Station from the

reference coordinates already fixed.


b Earthwork Excavation shall be taken up as per the approved Earth Work Excavation Methodology.


c A properly designed false steining may be provided where possible to ensure that the well cap is laid in dry conditions.


d Reinforcement tying of the Well Cap as per the approved drawing will be done for the Well Cap. Laps are provided in staggered manner wherever required.


f After the placing of formwork, Concreting will be done ensuing proper compaction. The top surface is made true to level.


g Dewatering shall be done wherever necessary for laying concrete.


h Proper curing arrangement shall be made.

---x---








12. SUB STRUCTURE



12.1 OBJECTIVE:

To out line the procedure for the method of construction of Sub structure conforming to approved drawings and project specifications.


12.2 CONSTRUCTION EQUIPMENT:

• Form work accessories

• Generator

• Welding transformer / Gas cutting set

• Batching plant

• Concrete pump / Crane and bucket

• Water pump


12.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of Sub structure works:


a The surface of foundation/well cap/pile cap shall be scraped with wire brush and all loose materials removed. In case reinforcing bars projecting from the foundations are coated with cement slurry, the same shall be removed by tapping, hammering or wire brushing. Proper constructions joints shall be provided.


b 2. The levels and dimensions of the sub-structure shall be marked using a total station on the foundation.


c Care shall be taken to remove all loose materials around reinforcements using compressor and by using compressor the exposed concrete surface of the foundation shall be wetted before the commencement of sub structure concreting.


d Weep holes in sufficient number and quality shall be provided as per the approved drawing in case of solid type abutment wall. Care should be taken that the weep holes are not displaced from its original position during concreting operations.


e Reinforcement tying and concreting operations of the sub-structure will be done in lifts of suitable heights as per the site conditions and depending upon the height of the substructure columns/shafts.


f Distribution steel shall be provided in lifts as per the approved construction drawing. Laps are provided in staggered manner wherever required. Formwork for the corresponding lift of the sub-structure will be placed in accordance with the drawing and true to the line and level.


g Proper care should be taken such that the formwork is properly tied so that it is not displaced from its position during concreting operations.


h Concrete of specified grade will be poured either using a crane & bucket or using a concrete pump as per the site conditions. Subsequent lifts of the sub-structure will be cast in the same manner.


i Concreting will be done ensuring proper compaction. The top surface of each lift shall be made rough to receive the next lift of sub-structure.


j Proper curing arrangements shall be made. No vertical joints shall be provided in the sub-structure. Care shall be taken that no weep holes get clogged with concrete during the concreting operations. If the weep holes get clogged with dirt, the same should be cleared after the removal of the formwork.


---x---





























13. FILTER MEDIA AND BACKFILLING



13.1 OBJECTIVE:

To out line the procedure for the method of construction of drainage filter media and backfilling behind bridge abutments and culverts conforming to approved drawings and project specifications.


13.2 CONSTRUCTION EQUIPMENT:

• JCB

• Dump trucks

• Vibro roller


13.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of drainage filter media and backfilling works:


a Excavate the area to be backfilled to the required angle and slope stated in the drawings.


b Squares of geotextile fabric will be secured over each of the weep holes to prevent the loss of fines.


c The approved filter media will be placed in layers concurrent with the backfill of the structure.


d Backfilling will be placed in layer and tested on accordance with the specification.


---x---















14. RCC GIRDER



14.1 OBJECTIVE:

To out line the procedure for the method of construction of RCC Girder conforming to approved drawings and project specifications.


14.2 CONSTRUCTION EQUIPMENT:

• Form work accessories

• Generator

• Welding transformer / Gas cutting set

• Batching plant

• Concrete pump / Crane and bucket


14.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of RCC Girder works:


a The bed for the RCC girders should be prepared as per the designed pre-camber.

b The Reinforcement tying for the RCC girders will be done as per the approved bar bending schedule and drawing.


c The side shutters for the RCC girders will be placed and aligned properly. Shutter vibrators will be fitted to the side shutters to ensure proper compaction.


d Concreting of RCC girders will be done either using a concrete pump or by using a crane & bucket. Proper care should be taken for effective compaction of concrete.


e The concreting operation will start from one end gradually filling up the girder.


f After completion of 24 hours from concreting. The formwork shall be so removed as not to cause any damage to concrete.

g Exposed surfaces of concrete shall be kept continuously in a damp or wet condition by covering with a layer of sacks, canvas or similar material and watered at regular intervals.


---x---







15. DECK SLAB



15.1 OBJECTIVE:

To outline the procedure for the method of construction of Deck slab conforming to approved drawings and project specifications.


15.2 CONSTRUCTION EQUIPMENT:

• Form work accessories

• Generator

• Welding transformer / Gas cutting set

• Batching plant

• Concrete pump / Crane and bucket


15.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of Deck slab works:


a After launching the RCC girders, The shuttering for diaphragms will be done by supporting between the RCC girders. All formwork will be done as per the approved design and drawings. The Reinforcement tying for the Diaphragms will be done as per the approved bar bending schedule and working drawing.


b The side shutters for the diaphragms will be placed and aligned properly.


c Concreting of diaphragms will be done.


d The formwork arrangement for the deck slab will be made as per the approved formwork drawing. Reinforcement tying will be made as per the approved bar bending schedule.


e Concreting will be done for the deck slab by using concrete pump or by using crane and bucket.


f Exposed surfaces of concrete shall be kept continuously in a damp or wet condition by covering with a layer of sacks, canvas or similar material and watered at regular intervals. After the concrete attains the required strength, the staging and formwork can be removed.


---x---







16. PSC GIRDER AND DECK SLAB



16.1 OBJECTIVE:

To out line the procedure for the method of construction of PSC Girder and Deck slab conforming to approved drawings and project specifications.


16.2 CONSTRUCTION EQUIPMENT:

• Form work accessories

• Multi-pull jacks with pressure gauges

• Grout mixer and grout pump

• Generator

• Welding transformer / Gas cutting set

• Batching plant

• Concrete pump / Crane and bucket


16.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of PSC Girder and Deck slab works:


a Shuttering for Pre-stressed Concrete T Girders and Slabs shall be fabricated at a centralized location and shifted to the site before the commencement of the work.


b The layout of cribs shall be marked on the ground after proper compaction and leveling the ground.


c Crib consisting of standard dimensions upto the required height shall be pre-fabricated.


d The crib towers shall be erected using crane as per the layout already marked on the ground. Longitudinal / Lateral bracing shall be done to the cribs for ensuring stability. The Main & Secondary girders shall be erected over the cribs.


e The bottom shutters for the Pre-stressed Concrete T Girders shall be placed over the secondary girders true to line, levels and dimensions.


f Reinforcement tying for the PSC girders and profiling of sheathing duct shall be done as per the approved drawings and bar bending schedule. Make sure the joints of all sheathing ducts shall be water tight.


g The side shutters for the PSC girders shall be placed and aligned properly. Shutter vibrators shall be fitted to the side shutters to ensure proper compaction.


h Concreting of PSC girders shall be done using required grade of concrete by using concrete pump or crane and bucket. The concreting operation shall start from one end gradually filling up the girders. Proper care should be taken to prevent entry of cement mortar into sheathing ducts at the time of concreting.


i After the completion of concerting operations, threading of HTS strands shall be done. After attaining the required strength of concrete as specified in the drawing, the first stage stressing & grouting shall be done.


j The formwork arrangement for the diaphragms & deck slab shall be made as per the approved drawings. Reinforcement tying and shuttering shall be completed for the diaphragms & deck slab and concreting done by using required grade of concrete, either with concrete pump or crane and bucket.


k Exposed surfaces of the concrete shall be kept continuously in damp or wet condition by covering with a layer of sack, canvas or similar material and watered at regular intervals.


l After the concrete attains the required strength, de-shuttering of the deck slab, girders & diaphragms shall be done.


m After the completion of concerting operations, threading of HTS strands shall be done. After attaining the required strength of concrete as specified in the drawing, the second stage stressing & grouting shall be done.


---x---




















17. BOX GIRDER



17.1 OBJECTIVE:

To out line the procedure for the method of construction of Box Girder conforming to approved drawings and project specifications.


17.2 CONSTRUCTION EQUIPMENT:

• Crane

• Form work accessories

• Multi-pull jacks with pressure gauges

• Grout mixer and grout pump

• Generator

• Welding transformer / Gas cutting set

• Batching plant

• Concrete pump / Crane and bucket


17.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for construction of Box Girder works:


a Reference points and benchmarks shall be transferred over the top of pier cap on either side with reference to the control points initially established.


b Staging shall be erected as per drawings. The supporting ground shall be first leveled, compacted and layout of the staging shall be marked. Main and Secondary girders shall be placed over the cribs. Formwork arrangement shall comprise of standard shutters, special shutters, props, tie-rods, wallers, etc.


c Fixing of soffit shuttering to proper line and level as per the drawings. Fixing of web out side shutters and end block shutters to the profile and dimensions as required. After shuttering, reinforcement of soffit bottom and web outer shall be fixed.


d Sheathing duct shall be placed in correct position and profile by providing suitable ladders and spacers. Sheathing shall be tied rigidly with such ladders/spacers so that they do not get disturbed during concerting. Anchorage cones shall be fixed at sheathing ends.


e Bottom haunch shuttering shall be placed after fixing of top reinforcement of soffit and inside reinforcement of web.


f Concreting of soffit and web (upto 100mm above bottom haunch) to be done with required grade of concrete.


g Remaining web inside shuttering shall be fixed 24 hours after concreting of soffit.


h Concreting for web shall be done upto 100mm below top haunch.


i After attaining required strength of concrete to web, first stage prestressing and grouting shall be done as per design requirements.


j Deck staging and shuttering over soffit slab concrete in line and level shall be fixed.


k Fixing of deck reinforcement and side shuttering shall be completed.


l Concreting for Deck shall be done upto 100mm below top haunch.


m After attaining required strength of concrete to deck, second stage prestressing and grouting shall be done as per design requirements.


n De-shuttering of deck slab and soffit shall be done as per specifications.


---x---



























18. FIXING OF POT / PTFE BEARINGS



18.1 OBJECTIVE:

To out line the procedure for the method of fixing of POT / PTFE bearings conforming to approved drawings and project specifications.


18.2 CONSTRUCTION EQUIPMENT:

• Lifting arrangement for POT / PTFE bearings


18.3 CONSTRUCTION METHODOLOGY:

The following sequence of activities shall be carried out for fixing POT / PTFE bearing fixing:


a The location of Pedestals on the abutment & pier cap shall be marked using total station from the control points. During concreting of the pedestals, dummy sleeves/dowels will be provided in the pedestals as per the dimensions of the POT/PTFE bearings.


b These dowels are provided in order to receive the attachment bolts connecting the bearing plates with the pedestals.


c The entire bearing assembly shall be placed above the pedestals true to the level and direction. During the first stage of grouting, the attachment bolts shall be grouted using Condextra GP2 grout.


d During the second stage of grouting, the remaining portion of the attachment bolts and the space between the pedestals and the bottom plate shall be grouted with Condextra GP2 grout. Care should be taken that during all these operations, the bearings are not displaced from its position.


e The entire bearing assembly shall be fixed in the direction as shown in the drawings. Temporary supporting arrangements shall be made for the bearings under the superstructure until the entire superstructure is complete and load transferred onto the bearings.


f Bearings shall be installed with care to ensure their correct functioning in accordance with the design for the whole structure. Bearings shall be so located as to avoid the accumulation of dirt and debris likely to interfere with their performance.


g Transfer of superstructure weight on to bearings shall not be allowed until sufficient strength has developed in the bedding material to resist the applied load. Suitable temporary supporting arrangements under the bearing base plates shall be made to accommodate thermal movement and elastic deformation of the incomplete superstructure, if necessary. Any voids left as a consequence of their removal shall be made good using the same type of bedding material, ie., GP2 grout mix.


---x---



 
 
 

Comments


Sudhanshu Civil

Ayachigram Road No-5 (W) ,Near Bariya Bus Stand, Muzaffarpur,Bihar 842001

LandMark- Little Feet Play School

Email

bottom of page